Source - LSE Regulatory
RNS Number : 7869W
Gresham House Energy Storage Fund
28 April 2021
 

28 April 2021

Gresham House Energy Storage Fund plc

(the "GRID" or the "Fund")

 

Quarterly NAV, Dividend and Factsheet publication

 

Q1 2021 NAV

 

Gresham House Energy Storage Fund Plc (LSE: GRID) (the "Fund") announces its NAV as at 31 March 2021 was £371.8m or 106.66p per ordinary share.

 

Dividend Declaration

 

The Board is pleased to announce a dividend of 1.75p per Ordinary Share for the period from 1 January 2021 to 31 March 2021. The dividend will be paid on 4 June 2021 to Shareholders on the register as at the close of business on 14 May 2021. The ex-dividend date is 13 May 2021.

 

Any such dividend payment to Shareholders may take the form of either dividend income or "qualifying interest income" which may be designated as an interest distribution for UK tax purposes and therefore subject to the interest streaming regime applicable to investment trusts. Of this dividend declared of 1.75 pence per Ordinary Share, 0.75 pence is declared as dividend income with 1.00 pence treated as qualifying interest income.

 

Q1 2021 Factsheet

 

The factsheet for the period ended 31 March 2021 is available at:

 

http://newenergy.greshamhouse.com/esfplc/

 

Extracted text of the commentary is set out below:

 

Financial highlights

 

From IPO to the end of March 2021, the Fund has delivered a share price total return of 27.3%, compared with a 7.9% total return from the FTSE All Share. The attribution of returns since inception is 14.5% to capital and 12.8% to income.

 

For the quarter ended 31 March 2021, the Fund's NAV was £371.8m or 106.66p per share, an increase of 3.70p per share in the quarter.

 

There was a 4.36p uplift from the revaluation of projects recently acquired (previously held at cost) while income in excess of dividend distributions in the quarter accounted for a 0.72p benefit. Partially offsetting this by 1.22p were a more cautious set of assumptions which included taking into account the impact of the corporation tax rate rising to 25% from 2023, as announced in the recent Budget.

 

Dividend coverage in Q1 2021 was c.1.3x despite a significant cash balance and, as such, the Fund remains committed to its dividend policy of 7.0p per share paid in equal quarterly instalments.

 

Finally, the Fund is exploring a debt facility which is expected to drive down its cost of capital which, in turn, is expected to be significantly accretive to GRID's overall return on capital, once any debt facility is fully deployed. The Fund will provide a further update in due course.

 

Portfolio activity & market outlook

 

The Investment Manager has had an active quarter, completing the acquisition of 80MW across four projects (Glassenbury Extension (10MW), Port of Tyne (35MW), Tynemouth (25MW) and Nevendon (10MW)) and a further 30MW since the quarter end in the form of Byers Brae near Livingston in Scotland.

 

The Investment Manager is also preparing to commence construction, subject to final due diligence, on a further 275MW across five projects (one is 100MW, two are 50MW and the other two are 40MW and 35MW respectively). The construction of these projects will fully commit all the funds raised in the November 2020 equity issue.

 

The Fund has a significant additional exclusive pipeline of 527MW across eight projects which will be built subject further debt and/or equity fundraising.

 

The market environment remains favourable as evidenced by the Fund's dividend coverage over Q1 2021. National Grid continues to procure more in the way of frequency response than there are projects in the market, with the suggestion that this will continue for several more months. Over the next two years, the level of procurement is expected to increase steadily.

 

In addition and long anticipated, the volatility in power markets has increased significantly, as a result of several instances of insufficient power driving power prices very high this winter. This was caused by low wind generation (which has come out much lower year-over-year due to low wind resource) and various other factors, including forecasting errors (of supply and demand, and outages of either generation capacity or inter-connectors at different times).

 

Portflio & Pipeline

 

Current portfolio

Project

Location

MW

Status

1.     Staunch

Staffordshire

20

Operational - 2018

2.     Rufford

Nottinghamshire

7

Operational - 2018

3.     Lockleaze

Bristol

15

Operational - 2018

4.     Littlebrook

Kent

8

Operational - 2018

5.     Roundponds

Wiltshire

20

Operational - 2018

6.     Wolverhampton

West Midlands

5

Operational - Q3 2019

7.     Glassenbury

Kent

40

Operational - Q4 20191

8.     Cleator

Cumbria

10

Operational - Q4 20191

9.     Red Scar

Lancashire

49

Operational - Q4 20191

10.   Bloxwich

West Midlands

41

Operational - Q3 2020

11.   Wickham Market

Suffolk

502

Operational - Q4 2020

12.   Thurcroft

South Yorkshire

50

Operational - Q4 2020

13.   Tynemouth

North Tyneside

25

Operational - Q1 20211

14.   Port of Tyne

Tyneside

35

Operational - Q1 20211

15.   Nevendon

Essex

10

Operational - Q1 20211

16.   Glassenbury Extension

Kent

10

Operational - Q1 20211

17.   Byers Brae

West Lothian

30

Operational - Q2 20211

Total Portfolio


425


1. Operational assets acquired from the market, showing when the project was acquired by the Fund and not the date of commissioning.

2. Asymmetric projects with lower Import Capacity versus its Export, all other projects have a symmetrical Export/Import Capacity.

 

Project

Location

MW

Commissioning

Committed Pipeline

18.   Project M

Swindon

100

Q1 2022e

19.   Project E

Leicester

50

Q1 2022e

20.   Project D

Manchester

50

Q1 2022e

21.   Coupar Angus

Co. Perth

40

Q1 2022e

22.   Arbroath

Co. Angus

35

Q1 2022e

Subsequent Pipeline

23.   Project Emerald

Republic of Ireland

c.40

2022

24.   Monet's Garden

North Yorkshire

50

2022

25.   Lister Drive

Merseyside

50

2022

26.   Project G

Northampton

50

2022

27.   Project P

Preston

50

2022

28.   Project E2

West Yorkshire

100+50

2022

29.   Project B

West Yorkshire

87

2022

30.   Project Y

York, N. Yorks

50

2022

Total Pipeline


c.802


 

For further information, please contact:

 

Gresham House New Energy

Ben Guest

 

 

+44 (0)20 3837 6270

Jefferies International Limited

Stuart Klein

Gaudi Le Roux

 

+44 (0)20 7029 8000

KL Communications

Charles Gorman

Camilla Esmund

Saurav Karia

 

+44 (0)20 3995 6673

 

JTC (UK) Limited as Company Secretary

Christopher Gibbons

 

+44 (0)203 846 9774

About the Company and the Manager:

Gresham House Energy Storage Fund plc owns a portfolio of utility-scale operational battery energy storage systems (known as BESS) located in Great Britain. The portfolio has a total capacity of 425MW. The Company is managed by Gresham House Asset Management Limited under the leadership of Ben Guest. The Company was admitted to trading on the London Stock Exchange (Specialist Fund Segment) on 13 November 2018 having raised £100 million of gross proceeds from investors. Including issuance under the Placing Programme, it has now raised a total of approximately £358 million of gross proceeds from investors.

 

The Gresham House New Energy team has a proven track record in developing and operating energy storage and other renewable assets having developed 264MW of Energy Storage Systems and approximately 290MW of predominantly ground-mounted solar projects. Gresham House Asset Management currently manages approximately 232MW of solar and wind energy projects.

 

Gresham House Asset Management is the FCA authorised operating business of Gresham House plc, a London Stock Exchange quoted specialist alternative asset manager. Gresham House is committed to operating responsibly and sustainably, taking the long view in delivering sustainable investment solutions.

www.greshamhouse.com

 

Definition of utility-scale battery energy storage systems

Utility-scale battery energy storage systems are the enabling infrastructure that will support the continued growth of renewable energy sources such as wind and solar, essential to the UK's stated target to reduce carbon emissions. They store excess energy generated by renewable energy sources and then release that stored energy back into the grid during peak hours when there is increased demand for it.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
DIVEAPLXAFNFEFA
Find out how to deal online from £1.50 in a SIPP, ISA or Dealing account. AJBell logo

Related Charts

Gresham House Energy Storage Fund PLC (GRID)

+0.30p (+0.72%)
delayed 17:27PM