Source - LSE Non-Regulatory
RNS Number : 7329Y
Kefi Gold and Copper PLC
18 January 2022
 

Reach

18 January 2022

KEFI Gold and Copper plc

("KEFI" or the "Company")

London Shareholder Forum

2pm, Monday 7 February 2022

KEFI (AIM: KEFI), the gold exploration and development company with projects in the Federal Democratic Republic of Ethiopia and the Kingdom of Saudi Arabia, is pleased to advise that it will host a shareholder forum at 2pm on Monday 7 February in London.

The event will take the format of a 15-minute presentation followed by a 15-minute open forum discussion on each of three topics: Tulu Kapi Gold Mines in Ethiopia, Gold and Minerals in Saudi Arabia and KEFI Gold and Copper plc more generally.  The forum will be hosted by members of the KEFI Board and senior management, and will be open for attendance by shareholders both virtually and in person. The London venue details and how to access the event online will be announced in due course.

Additionally, KEFI has uploaded to its website (https://www.kefi-minerals.com) a presentation it is making today to the Company's Sydney-based shareholders.

Enquiries

KEFI Gold and Copper plc

 

Harry Anagnostaras-Adams (Managing Director)

+357 99457843

John Leach (Finance Director)

+357 99208130

SP Angel Corporate Finance LLP (Nominated Adviser and Joint Broker)

+44 (0) 20 3470 0470

Jeff Keating, Adam Cowl

 

Tavira Securities Limited (Joint Broker)

+44 (0) 20 7100 5100

Oliver Stansfield, Jonathan Evans

 

WH Ireland Limited (Joint Broker)

+44 (0) 20 7220 1666

Adrian Hadden, Andrew de Andrade

 

IFC Advisory Ltd (Financial PR and IR)

+44 (0) 20 3934 6630

Tim Metcalfe, Florence Chandler

 

 

Notes to Editor

KEFI Gold and Copper plc

KEFI is focused primarily on the development of the Tulu Kapi Gold Project in Ethiopia and its pipeline of highly prospective exploration projects in the Arabian-Nubian Shield. KEFI targets that production at Tulu Kapi will generate cash flows for capital repayments, further exploration and dividends to shareholders.

The following tabular summary presents KEFI's estimated share of the project NPV's :

 

Tulu Kapi

Hawiah

Jibal Qutman

Total

Issued

Pence Per

 

NPV

NPV

NPV

NPV

Shares

Share

Net Present Value

for KEFI

 

 

 

 

 

 

    30 June 20

£114 mill

N.A

N.A

£114 mill

1,867 mill

6

    31 December 20

£164 mill

£80 mill

N.A

£244 mill

1,876 mill

13

    30 June 21

£191 mill

£80 mill

N.A

£271 mill

2,159 mill

13

    10 January 22

£191 mill

£124 mill

£33 mill

£348 mill

2,939 mill

12

 

 

 

 

 

 

 

Footnotes:

 

 

 

 

 

 

Gold Price is US$1,830/oz

 

 

 

 

 

 

Copper Price is: US$9,750/t

 

Assumed exchange rate was rate US$1.35:£1.00.

 

Zinc Price is US$3,590/t

 

 

 

 

 

 

Silver Price is US$23/oz

 

 

 

 

 

 

 

 

 

 

 

 

 

Explanatory Notes:

 

 

 

 

 

 

NPV is derived by KEFI using independently created financial models of net cash flows after tax and debt service, using a discount rate of 8%.

Tulu Kapi open pit model is based on the Definitive Feasibility Study ("DFS") as updated for any refinements during project contracting;

Tulu Kapi underground mine model is based on the Preliminary Economic Assessment ("PEA");

 

 

Hawiah at this stage assumes preliminary mine modelling for open pit and underground because the MRE has only recently been updated;

 

KEFI Gold and Copper in Ethiopia

Ethiopia is currently undergoing a remarkable transformation both politically and economically.

The Tulu Kapi gold project in western Ethiopia is being progressed towards development, following a grant of a Mining Licence in April 2015.

The Company has now refined contractual terms for project construction and operation. Estimates include open pit gold production of c. 140,000oz pa for a 7-year period. All-in Sustaining Costs (including operating, sustaining capital and closure but not including leasing and other financing charges) remain c. US$800/oz. Tulu Kapi's Ore Reserve estimate totals 15.4Mt at 2.1g/t gold, containing 1.1Moz.

All aspects of the Tulu Kapi (open pit) gold project have been reported in compliance with the JORC Code (2012) and subjected to reviews by appropriate independent experts.

A Preliminary Economic Assessment has been published that indicates the economic attractiveness of mining the underground deposit adjacent to the Tulu Kapi open pit, after the start-up of the open pit and after positive cash flows have begun to repay project debts. An area of over 1,000 square kilometres adjacent to Tulu Kapi has been reserved for exploration by KEFI's wholly-owned Ethiopian subsidiaries upon commencement of development by TKGM, with a view to adding satellite deposits to development and production plans.

KEFI Gold and Copper in the Kingdom of Saudi Arabia

In 2009, KEFI formed Gold & Minerals Limited ("G&M") in Saudi Arabia with local Saudi partner, ARTAR, to explore for gold and associated metals in the Arabian-Nubian Shield. KEFI has a 31.2% interest in G&M and is the operating partner.

ARTAR, on behalf of G&M, and G&M directly hold over 16 Exploration Licence (EL) applications pending the introduction of the new Mining Law. These new regulations have recently been proclaimed and G&M now holds 3 EL's.  ELs are renewable for up to three years and bestow the exclusive right to explore and to obtain a 30-year exploitation (mining) licence within the area.

In addition, G&M has a Mining Licence Application over the Jibal Qutman Gold Project which recent informal indications by the authorities provide some confidence that the licence will be granted in 2022.

 

 

This information is provided by Reach, the non-regulatory press release distribution service of RNS, part of the London Stock Exchange. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

Reach is a non-regulatory news service. By using this service an issuer is confirming that the information contained within this announcement is of a non-regulatory nature. Reach announcements are identified with an orange label and the word “Reach” in the source column of the News Explorer pages of London Stock Exchange’s website so that they are distinguished from the RNS UK regulatory service. Other vendors subscribing for Reach press releases may use a different method to distinguish Reach announcements from UK regulatory news.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
NRAFLFITLEIDLIF
Find out how to deal online from £1.50 in a SIPP, ISA or Dealing account. AJ Bell logo

Related Charts

Kefi Gold And Copper PLC (KEFI)

+0.03p (+5.19%)
delayed 13:45PM